The Katwe Youth Resource Centre construction has begun

The Katwe Youth Resource Centre under construction (Phase 1)

Katwe Youth Resource Centre under construction
Katwe Youth Resource Centre under construction

The Namukuma village is very excited that construction is under way. The village elder suggested we file for the charity documents on the new location instead of for the Centre in Kampala.

“It will be easier to get it legally documented in my district. It is very difficult to change district’s at a later date.”

Supply shortage for continued construction
Supply shortage for continued construction

The supplies are coming up a little short
Labor expenses were a little
More than expected, so it will carry on to next month. Ssebadduka Isaac is going to continue construction on his own until Friday. Funds for labor are In short supply.

4 more truck loads of brick are needed in order to prepare for the roof.

Electricity is on it’s way, it will be in the Namukuma village in Ugonda in about 4 months. The main road only 3 miles from the Namukuma village is being repaired and rebuilt. Namukuma village is located some 26 miles from Kampala the capital of Ugonda.

Ssebadduka Isaac will continue as best he can with the work
Ssebadduka Isaac will continue as best he can with the work